Alternative Analysis is the technique used under the process Estimate Activity Resources process.
I know many of you must be aspiring to become successful project managers in your career which can be the stepping stone to become good leaders. How you can achieve this? Yes, by implementation which is critical. And to distinguish from others you need to have some kind of credentials which can be obtained through certifications like PMP, ITIL. To know more about or to get prepared for the same, you can always approach me @ bksprasad@yahoo.com or subramanya.bks@gmail.com
Alternative Analysis is the technique used under the process Estimate Activity Resources process.
Suppose you want to reach office 9 in the morning. Every day it may take about an hour to reach. So usually you start at 8 in the morning. But let us you know that tomorrow there is a blockage of road due to some rally in the usual route, you need to take alternative route. But it takes more time. So what you do? Instead of starting at 8 in the morning, you plan to start at may be 7.30 in the morning. This half an hour is called lead. You are advancing an activity.
Lag is waiting period between two activities. Once you construct ground floor, you need to wait for two days before starting the first floor. This waiting period which is 2 days is called lag.
Lead and Lag technique is used under processes like Sequence Activities, Develop Schedule and Control Schedule processes.
Mandatory: It is the used when it is inherent to the nature. For example construction of the wall depends on finishing of the foundation. You can’t think of the other way. This is also called as hard logic.
Discretionary: In the situation there are some activities which can be carried out either way based on the logistics availability or based on the best practices. It is based on the preference. This is also called as preferred or soft logic. For example if you want to provide the training to the operation team about the project, the training can happen after the transition or before the transition. The training can be imparted based on the logistics availability and the people.
External: This is nothing but where you are dependent on the external environment or element where you don’t have any control. For example, approval from the government organization or materials from the vendor.
Internal: Here the dependency is within the project. For example funding, resource availability, etc…
Dependency Determination technique is used under the process Sequence Activities.
There are four types of relationships used when constructing schedule model using Precedence Diagramming Method.
Finish to Start (FS): Starting of an activity depends on the finishing of the previous activity. For example starting of the second shift depends on finishing of the first shift.
Start to Start (SS): Starting of an activity depends on the starting of the other activity. Here two activities run in parallel. For example starting of the training depends on starting of the assembly of the delegates. Here I am assuming trainer need not to wait for all the delegates to come. Even one delegate is enough to start the training.
Finish to Finish (FF): Finishing of an activity depends on finishing of the other activity. Again here two activities run in parallel. For example finishing of project closing depends on finishing of lessons learned documentation. Lessons learned activity might have started earlier itself, but by the time project closing finishes lessons learned should finish or at the same time.
Start to Finish (SF): Finishing of an activity depends on starting of the other activity. For example the finishing of first shift depends on starting of the second shift.
SF is very rarely used and FS is frequently used.
Also AOA is outdated. AOA can’t use all the four types of relationships. It can use only FS relationship whereas AON uses all the four types of relationships.
Precedence Diagramming Method technique is used under the process Sequence Activities.
Rolling Wave Planning technique is used under Define Activities process.
Variance Analysis technique is used under the process Control Scope process.
Inspection is used as technique under Control Quality and Validate Scope processes. Also it is used under Control Procurement process with technique name as Inspections and Audits. But in general Inspection to be carried out throughout the project as part of Monitoring and Controlling process group as per the plan.
Now the question is what is the meaning of manage? Manage means one should be able to estimate for schedule, cost and track the same. So the level of decomposition differs from project to project based on complexity in terms of effort. Typically 8/80 rule is used in general. The meaning of this is no work package should be less than 8 hours and no work package should be greater than 80 hours. So divide the scope in such a way that the work package should be in the range of 8 hours to 80 hours.
Decomposition can be done using box type or using tools like MS Project. Engineering projects uses ISO standards for decomposition. It is organization specific.
Decomposition technique is used under two processes. One in Create WBS and the other is Define Activities.
Alternative Generations technique is used under process Define Scope.
Product Analysis technique is used under process Define Scope.
Document Analysis technique is used under process Collect Requirements.
For example, as an user (Actor) I want to know my Body Mass Index (BMI). I will provide the input, to system which can be a simulator, the height and weight. The system throws the output which is BMI. Using this BMI, I will decide what action should be taken. Either increase weight or decrease weight.
Context Diagrams is used under the processes Collect Requirements.