Scheduling Tool is used as a technique under the processes Develop Schedule and Control Schedule.
I know many of you must be aspiring to become successful project managers in your career which can be the stepping stone to become good leaders. How you can achieve this? Yes, by implementation which is critical. And to distinguish from others you need to have some kind of credentials which can be obtained through certifications like PMP, ITIL. To know more about or to get prepared for the same, you can always approach me @ bksprasad@yahoo.com or subramanya.bks@gmail.com
Scheduling Tool is used as a technique under the processes Develop Schedule and Control Schedule.
Crashing is nothing but adding the resources. The impact is it increases the cost and or risk.
Fast tracking is carrying out activities in parallel. But this technique results in quality reduction, rework and increases the risk.
Crashing and Fast tracking should be applied to critical path activities. Then only it makes sense.
Schedule Compression technique is used under the processes Develop Schedule and Control Schedule.
What-If Scenario Analysis is used to evaluate the different scenarios to see the effect on project objectives like schedule. For example what happens if a particular resource is not available, what happens if a vendor is not going to deliver the raw materials on time, what happens if a particular work package postponed to later date… The outcome can be used to assess and take future action like parking the contingency.
Simulation is used to get the probability distribution using different techniques like PERT. The most widely used tool is called Monte Carlo analysis.
Modeling Techniques is used under the processes Develop Schedule process, Control Schedule and Perform Quantitative Risk Analysis.
Resource leveling is used based on the availability of resources, resource usage. This will ensure full utilization of the resources. The result of the resource leveling usually is critical path changes.
Resource smoothing adjusts activities in such a way resources do not exceed predefined resource limits. This will not impact critical path but the activities in the non-critical path may be delayed by consuming the total float.
Resource Optimization Techniques is used under the processes Develop Schedule process and Control Schedule.
Critical Chain Method is used in Develop Schedule process.
1. Draw the network diagram based on the dependencies of the activities.
2. Find the number of the paths from the network diagram. Number of paths means the paths which are traversing from start of the project to the end of the project.
3. Find the duration of each path by adding the duration of all the activities from the respective path.
4. The highest duration path is the critical path. And this itself is the duration of the project.
After finding the critical path one can find the total float or slack. Total float is nothing but how much an activity can be delayed without affecting the overall schedule of the project or the immediate start of the successor activity. How to calculate the total float? You need to follow two steps. One is forward pass and the second is backward pass. Forward pass is moving from start of the project by adding the duration of each of the activity and backward pass is moving from end of the project to the start of the project by subtracting the duration of each activity. After carrying out these steps you will find four values Early Start (ES), Early Finish (EF), Late Start (LS) and Late Finish (LF).
EF=ES + duration of the activity LS=LF - duration of the activity
Calculate total float using the formula
Total Float=LS-ES or LF-EF
The critical path activities will be always having zero total float whereas non critical path activities will be having float.
Critical Path method is used in Develop Schedule process.
Schedule Network Analysis is used under Develop Schedule process.
Contingency reserve can be derived based on quantitative risk analysis or based on standard deviation method or using organizational practices by putting some percentages.
Management reserve will be under management control and again this is derived based on unforeseen things which may happen to the project considering experience, historical data, contract terms and conditions, enterprise environmental factors, etc…
Reserve Analysis technique is used under the processes Estimate Activity Duration, Estimate Costs, Control Costs and Control Risks.
(P+4M+O)/6 which is Beta distribution or (P+M+O)/3 which is Triangular distribution.
Beta distribution is the weighted average which is also called as PERT (Program Evaluation and Review Technique).
Under the PERT one can derive the standard deviation and variance.Standard Deviation for an activity is (P-O)/6 and Variance is Standard deviation Square.
Three Point Estimating technique is used under the processes Estimate Activity Duration and Estimate Costs.
Parametric Estimating technique is used under processes Estimate Activity Duration, Estimate Costs processes.
Analogous Estimating technique is used under processes Estimate Activity Duration, Estimate Costs processes.
Bottom-Up Estimating is the most accurate estimation technique but is time consuming.
Bottom-Up Estimating technique is used under the processes Estimate Activity Resources and Estimate Costs.
For example, for a particular human resource with specific skill and experience what he/she may charge in a specific country?
Published estimating Data is the technique used under the process Estimate Activity Resources process.