Thursday, February 16, 2012

PMP Formulas



Formulas to be known
for the PMP examinations
Here is the table having important formulas to be known for
the examination



















If you observe in the above table, EAC is calculated in 4
different ways depending on the situation. Here is the explanation.
1. EAC=BAC/CPI
: This is used when there is no variance from the BAC occurred or you are going
to carry out the project at the same rate of money spending.
2. EAC=AC+ETC:
This is used when the original estimate is faulty or damaged.
3. EAC=AC+(BAC-EV):
This is basically actual cost plus the remaining worth of work to be
accomplished or the situation is of atypical in nature.
4. EAC=AC+(BAC-EV)/SPI*CPI:
This is used when the situation is typical with cost performance is very bad
and the completion date to be hit.

2 comments:

  1. Hi Subramanayam,

    The post on PMP Formulas by you is really excellent .Good job!! keep it up

    ReplyDelete
  2. Thanks for the valuable input on PMP Certification you contributed on the forum. It is really helpful

    ReplyDelete

Thanks for your comments. Will get back to you