Formulas to be known
for the PMP examinations
Here is the table having important formulas to be known for
the examination
If you observe in the above table, EAC is calculated in 4
different ways depending on the situation. Here is the explanation.
1. EAC=BAC/CPI
: This is used when there is no variance from the BAC occurred or you are going
to carry out the project at the same rate of money spending.
2. EAC=AC+ETC:
This is used when the original estimate is faulty or damaged.
3. EAC=AC+(BAC-EV):
This is basically actual cost plus the remaining worth of work to be
accomplished or the situation is of atypical in nature.
4. EAC=AC+(BAC-EV)/SPI*CPI:
This is used when the situation is typical with cost performance is very bad
and the completion date to be hit.
Hi Subramanayam,
ReplyDeleteThe post on PMP Formulas by you is really excellent .Good job!! keep it up
Thanks for the valuable input on PMP Certification you contributed on the forum. It is really helpful
ReplyDelete